Re: Using SAP QM & PM for Enviro monitoring for items like water, rooms

Former Member
0 Kudos

I am also using functional location and using the PM as a task list to generate an inspection lot (14).  However, I am having issues getting  the inspection lot to have a end date. The lots are only generating a 0 day cycle time for the lab.

Accepted Solutions (0)

Answers (2)

Answers (2)

Former Member
0 Kudos

Hope, Inspection start date & End date falls on same date.

Think, its being copied from PM Order Basic Start date & End Date in Header.

If you want to have some date period, you can make use of Priority field in Maintenance Plan (if you are generating orders through plan). Else, select the priority in Calibration PM Order directly.

Still, you face that problem, check the Scheduling Parameters for the Order type & Plant combination. Maintain some no. of hours in operation & do the scheduling in order.

Former Member
0 Kudos

Lynn Edgar,

Suggest you to open a new thread for your query.

former_member42743
Active Contributor
0 Kudos

Thanks Maheswaran,

I split the topic off for her.

Craig