on 04-01-2014 12:04 AM
Hi,
Check the whether the selection screen inputs of CJI4 again e.g. your version, Period, Fiscal year, WBSE & Cost element are correct.
Regards
Shishir
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Hi,
I can see all the fields, your version, Period, Fiscal year, WBSE & Cost element are correct.
My question is Do i need to input cost element as mandatory with WBS element in CJR2 bacause for some wbs elements cost forecasting is done without cost elements.
How can i do cost forecasting only with wbs element in CJR2 without giving cost element.
Please suggest,
Thanks,
Hi Pavan,
I think you are simultaneously questioning two similar threads at the same time which are creating confusion. I went to your thread http://scn.sap.com/thread/3529051
and found that it is very similar to this one and experts have already gave you the solution there.
In cjr2, you need to give the cost element. Else you can go with CJ40 as suggested earlier also.
Regards,
Amit
User | Count |
---|---|
108 | |
12 | |
11 | |
6 | |
5 | |
4 | |
3 | |
3 | |
3 | |
3 |
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.