on 03-30-2014 11:55 AM
Dear Experts,
I am facing once issue related to UOM in SRM. The issue is describe below
We are having classic scenario and using PI.
1. If a PR having material with UOM having a different ISO code, for eg
if Material A is having Base Unit of measure as Nos and Nos is having ISO code EA.
while replicating PR always EA (ISO COde) is getting passed through PI with material data and ending up with error: Mismatch with XML and SRM UOM.
2. Similarly if I am trying to create PO/Contract from SRM to ECC, with a material having base unit which is having different ISO code,
Always ISO code is passed to ECC through PI. It is ending with error finally in ECC.
Altough in both the cases Material is maintained with same UOM in both the system.
Request you to please help me in resolving this issue. Thanking you in advance.
Thanks and Regards,
Manil
Hi Jinesh,
Did u find the solution for this? If yes, plz share it.
Thanks,
Rudresh
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Hi Manil,
Please check both the systems - SRM as well as ECC for ISO codes. The ISO codes should be same in both the systems.
1. GO to transaction - CUNI or table T006 in both the system
2. Check for the respective UoM failing. ISO codes should be same.
3. If ISO code is not same, please maintain in either system which are standard ISO codes.
4. This will resolve your problem.
5. Temporary workaround - Change the UoM to something which is standard and repost the SC.
Thanks,
From RBEI,
Snehal
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Hi Manil,
UOM and its ISO code should be matched consistently in both SRM and ECC systems.
Regards,
Ivy