Resources - Date outside of planning period

Former Member
0 Kudos

Hi SAP Experts,

I check my capacity profile of the resource 186WC1 in SAP APO 7.0 system and found out that there are dates which are outside of the planning period (the purple dates). Its factory calendar is US which is up to 2020.

Could you please show me how to extend or modify the planning period in SAP APO system ?

Thank you in advance.

Danny

Accepted Solutions (1)

Accepted Solutions (1)

Former Member
0 Kudos

Hi Danny,

I hope you have long enough horizon in the future for your storage bucket profile. Please re-initialize your planning area for your version '000'.

Once done, you run the report '/SAPAPO/CRES_CAPACITY_LENGTHEN' for your planning version '000' and the resource 'W186WC2_1861_002'.

This should resolve your issue.

Thanks,

Satyajit

Former Member
0 Kudos

Hi Satyajit,

Thank you for your suggestion. Actually, the system calculates the planning periods based on planning parameters and created date of resources in SAP liveCache, so I re-transferred the work centre from R/3 to APO to update its saved date in liveCache. As a result, the planning period of resource is accordingly updated.

Cheers,

Danny