on 03-28-2014 4:44 AM
Hi,
I need to transfer the PR from ECC to SRM..?
Automatic - Implement the BADI ME_REQ_SOURCING_CUST
Manually - Through CPPR application without implementing the above BADI? Is that True..??
I heard that without BADI implementation, we ca transfer PR from ECC and Create a RFx. Kindly explain me..
Thanks in advance.
Dear Tamil,
Refer to below link. it will help you.
From EHP4/ERP 6.0 requirements can be transferred using Collective Processing of Purchase Requisition (CPPR) .In both ways we can handle custom checks like Purchase Group/Material Group validations.
As per Collective Processing of Purchase Requisition handling of Direct Material possible in SRM .Here creation of Purchase Order done in SRM system where deployment scenario is “Extended Classic” .
·
Regards,
Amit
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Hi Tamil
PLease check the below :
PI is mandatory for CPPR in SRM 7 with ECC 6.0 Enhpk 4.0. You need to use harmonized role for that.
However, in the latest SRM release SRM 7 Enhpk 1 with ECC 6.0 Enhpk 5, lot of PI independent ESOA services have been introduced. You may avoid using PI if you are going for latest SRM release.
http://scn.sap.com/thread/2082314
http://wiki.scn.sap.com/wiki/display/SRM/CPPR+Configuration
http://help.sap.com/SCENARIOS_BUS2008/helpdata/EN/61/1775eecdd343c9b4c28db68d1d4bd8/content.htm