Commitment cost based on network activity.

Former Member
0 Kudos

Hi Friends,

In one custom report. For the WBS element for specific network & Activity. How I can get Commitment cost.

Kindly help me on the logic.

Thanks,

Kiran

Accepted Solutions (1)

Accepted Solutions (1)

varshal_kachole3
Active Contributor
0 Kudos

Hi Kiran,

Table COOI stores the commitment costs.

To begin with, this should help you as an input to develop custom report.

Kindly explore SDN for more details on how to read COOI as per your requirement.

Hope it helps.

Thanks and Regards,

Varshal Kachole

The SCN Rules of Engagement

Former Member
0 Kudos

Hi Varshal,

Can you let me know which column should I consider of COOI

varshal_kachole3
Active Contributor
0 Kudos

Hi,

I am unsure about your question!

But Plan/LC-COOI-ORGWTH should be the one you are referring to.

Thank you and Regards,

Varshal Kachole

The SCN Rules of Engagement

Answers (5)

Answers (5)

Former Member
0 Kudos

Hi,

Check:

S_ALR_87100187 Commitments for Each Month (Current Fiscal Year)

S_ALR_87013533 Plan/Actual/Commitment/Rem.Plan/Assigned

S_ALR_87013537 Commitment Detail

S_ALR_87013558 Budget/Actual/Commitment/Rem Plan/Assigned


Also CJI5 is the basic report to get the commitment line item wise details against Project Objects.


Regards

Shishir

Former Member
0 Kudos

Hello Kiran,

You can also refer report S_ALR_87013558 and check commitment column.

As suggested by others , CJI5 is the basic transaction mostly used for checking  commitments.

Please search the forum or google it before posting any querry...

Regards

Tushar

former_member189209
Active Contributor
0 Kudos

Hi,

User T code _ S_ALR_87013542 & CJi5

Mahesh

former_member189209
Active Contributor
0 Kudos

Hi,

after execute S_ALR_87013542 -  double click on commitment amount - then you will get line items details also

Mahesh


0 Kudos

Hi...

cji5 works perfectly to show you commitments (po, pr etc ) with remaining values etc...It works like a charm..

Cheers

Panagiotis

Former Member
0 Kudos

Hi,

Did you check CJI5 report to view the commitment costs. Then you search the forum and you will lot of discussion in the past on this topic.

Regards,

Sudhakar

Former Member
0 Kudos

Which column is to be considered of CJI5

Former Member
0 Kudos

Hi, Please navigate to find out.

Thanks,

Sudhakar

0 Kudos

Hi..

cji5 is extremely straight transaction ...it has columns named ex "Value TranCurr" ..indicating the remaining commitment value...there are columns with quantities and also the plan amounts..

You should try and run it against a project.

Panagiotis