we are importing SAPKB70030, SAPKB70030 and SAPKA70030 into our LEH. LEH is a HCM developer system running on zLinux with database DB2 on zOS.


The update is stuck at the "move nametab" on the table TTONFTVZZBEPP. This table is a lock, which can currently not be resolved.

Because it is an empty table, we would like to skip this action. There is a possibility?

Thank you for your efforts.

Regards

Hartmut Wagner

Accepted Solutions (1)

Accepted Solutions (1)

Matt_Fraser
Active Contributor
0 Kudos

Hartmut,

Are you getting any other errors?  SQL errors, for instance?  Also, are these the only two SP's in your queue, or are you doing others up to these?  Note 822379 (Known problems with Support Packages in SAP NW 7.0x AS ABAP) mentions several known errors in the IMPORT_PROPER phase, one of which is specific to DB2, but none specific to the SP's you mention.

If nothing you see in that Note applies to your situation, then I would say you need to find a way to resolve the table lock.

Best regards,

Matt

Former Member
0 Kudos

Matt,

After we unlock the tables, we were able to continue the SPAM. Thank you for the tip.