Hi Experts,

We are planning to schedule a availablility Planning in a JDBC channel.

We want to run the channel 1st day of every month from 12-18.

When we save it after providing the details, we are getting the below expection.

Enter a valid duration; the start time must not be before the current time

Regards,

Swathika.

Accepted Solutions (0)

Answers (2)

Answers (2)

iaki_vila
Active Contributor
0 Kudos

HI Swathika,

In addition to Indrajit, there are examples in or the SAP.help documentation https://help.sap.com/saphelp_nwpi71/helpdata/en/46/ad6cfeb5492a86e10000000a1553f6/content.htm

Regards.

Former Member
0 Kudos

Hi Inaki/Indrajit,

If i give tomo date as start and end date, we are able to successfully create it.

As suggested by you, if we give the past or future date as start and End date we are getting the exception as specified above.

Kindly guide.

Regards,

Swathika.

Former Member
0 Kudos

Hi Swathika

Yes the system expect that the start and end date will be any date in the current month after current date.

So you can choose start date as 25 ,26,27,28,29,30 and 31 of march.

But it is not allowing to enter any date after march 2014 or any date before today's date.

So you can configure the scheduling on April 1st and at the time it will allow you to save.

For testing purposed you can choose the start time as any date after today's date.

Former Member
0 Kudos

Hi

Create new schedule type monthly.

Schedule the channel as

The channel will start at 1st april 2014 at 12 and it will turn of at 18 PM.

This will happen in 1st day of every month until april 2015.

Hope this is clear.