While replicating the PO by executing Function Module 'bbp_pd_po_transfer_exec' i got this error:
'Plant 1288 and storage location D.MÉ not defined'
Could anyone help me?
thanks,
Meriem.
i found the storage location written in bbp_pd in the item line.
i deleted it by debugging and i replicated the PO.
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Can you try to debug?
I think it is easy to check which system the error message is from
Regards,
Hayashi
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Hello Hayashi,
I know that the error is coming from ECC.
the message exists in 7 programs (/PBS/FMMEXE01, /PBS/LMEQRF03, FMMEXE01_LGORT, LMEOUTP66, LMEQRF2I,
LMEREF35, LMEXFU23).
I am getting this error while replicating the PO using the function module 'BBP_PD_PO_TRANSFER_EXEC'.
I tried to debug but i couldn't find the link between SRM and ECC.
Do you have any idea which program is called by SRM?
thanks,
Meriem.
Hello Meriem,
Please refer to the thread http://scn.sap.com/thread/3498316 and my post which explains the process of debugging erroneous POs.
Regards,
Arun Singh
Hello Meriem,
The message is E005(ME) in ECC.
Please have a look at table T001L and ensure entries are correct. I believe that an entry is missing in this table for plant-storage location relationship.
Regards,
Arun Singh
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Hi
Can you check if the plant is added in the attributes of the user creating the shopping cart.
Implementation Guide for R/3 Customizing (IMG) -> Enterprise Structure -> Definition -> Logistics - General> Assign plant to company code
Implementation Guide for R/3 Customizing (IMG) -> Enterprise Structure -> Assignment -> Materials Management -> Assign purchasing organization to company code
Implementation Guide for R/3 Customizing (IMG) -> Enterprise Structure -> Assignment > Materials Management-> Assign purchasing organization to plant
cross check all the above settings. May be the links below will help you.
storage location not defined for delivery item | SCN
https://scn.sap.com/thread/1887010
Hope it helps.
Regards
Bash