Ex:Shipment has done on 19/03/2014 and while you are going to create PGI of that delivery on 22/03/2014 ,you meant to say that system has to take PGI date as 19/03/2014 as per shipment date not on current goods issue date 22/03/2014?
Thanks,
Naren
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Dear Narendra,
my user created financial document in vx11n againest letter of credits and user given the latest shipment date 15-03-2014, so that user can do the PGI from 27-02-2014(FD avilable date) to 15-03-2014(latest shipment date). so if user did next to this date system will thorugh the error . but in my seceniro system accepted the PGI on 18-03-2014 .this is my issue ,kindly give the solution .