on 03-19-2014 1:41 PM
It seems that I've solved this issue. To get it work:
1. Select checkbox Time Recording and Travel Expenses via CATS for project type. Path: SPRO —> SAP Customizing Implementation Guide —> SAP Portfolio and Project Management —> Project Management —> Structure => Define Project Types
2. Run/schedule a synchronization with the report DPR_CATS_CPR_TRANSF (Transfer of CATS Itemizations to Project Management Application).
Time Recording from a Request for Change to a PPM ProjectTask - Working with Projects - SAP Library
Regards,
Alex
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Hi Cassoke,
This can be achieved by creating a 'Field Control' profile and attaching the same to the project type.
This is done through customisation settings in the below path.
SPRO--》PPM--》Project management --》Global enhancements--》Setup field control.
Create a new profile with selection of project element 'task'
Condition : Object is released
Field : Confirmed work
Fulfilled : display mode
Non-fulfilled : display mode
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
User | Count |
---|---|
4 | |
4 | |
1 | |
1 | |
1 | |
1 | |
1 | |
1 | |
1 | |
1 |
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.