Hi, While trying to CIF PPM in APO 5.0, getting the error "Activity Network is not complete"
Message no /SAPAPO/PPM_MAINTAIN517
Diagnosis
The activity network does not include all activities of the PPM.
Procedure
Check that the activity relationships of your PPMs are complete.
Any remedy??
Regards, Bhavesh
Hi Bhavesh,
You need to check the activity relationships. Suggest you check each activitiy relationships (SS, SF, FS, FF) from Reference Type field and draw them out on a piece of paper to see if there is any activity which is not properly linked.
Remedy is to rectify any missing relationship in the PPM.
Thanks,
Somnath