on 03-17-2014 9:44 PM
Hi Guys,
Multiple PPMs are available in the system , When the firm planned order created in /sapapo/rrp3 period tab for the PPM3 after sending the planned orders to ECC, the PPM got removed from the planned orders.
All PPM have validity period from 01/01/2013 to 30/12/2039 and lot size of 0 to 9999999.
There is no user exit to modify the source of supply, any idea what will cause this change.
You help very much appreciated.
BR
Thamizh
Thamizh,
Does the Production Version for this material/plant still exist in ECC?
Has the most recent Production Version been verified in ECC?
Is the Production Version in ECC identical to the PPM in SCM?
Any time the SCM PDD becomes inconsistent with the ECC PV, you may get these symptoms. You can test this by
Deleting all the Planned orders for a single material/plant in both ECC and SCM
Delete the PDD for this material in SCM
Re-CIF the PDD to SCM using RIMODINI against the appropriate model
Re-create one planned order in SCM against this material and send to ECC. If you get a valid source of supply in the new planned order (which has the ECC order number), then you should suspect that your PDDs have lost consistency with the PVs.
Best Regards,
DB49
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
User | Count |
---|---|
9 | |
4 | |
3 | |
2 | |
2 | |
1 | |
1 | |
1 | |
1 | |
1 |
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.