I have a scenario where i need to create a billing plan for more than 2 years in a sales order. Could the experts advice how to achieve this in billing plan(periodic). When i enter the start and end date say 01.01.2014 to 31.12.2016 in the billing plan. I could only get the dates till 31.03.2015 and not till 31.12.2016

Accepted Solutions (1)

Accepted Solutions (1)

naveen_kaluti
Active Participant
0 Kudos

Hello,

Create a new "Rule table for date determination" using tcode "OVBS" and provide below inputs:

Time Period: 2

Time Unit: 4

assign this to End date field in your billing plan.

Hope this resolves your issue.

Regards

Naveen K.

Answers (2)

Answers (2)

Former Member
0 Kudos

Hi

Change  Horizon in your billing plan 02 for 2 year contract, before that u have create  Rule table foe date determination reference to Mr. Naveen K

Regards

Christin B

former_member184701
Active Contributor
0 Kudos

did you check the relevant factory calendar?