Here is the scenario:
No budgeting is used in PS ie. no budget profile is assigned to projects.
Initially we are planning cost and revenue for the project and coping these plan value in version "02 : Project Baseline Budget" made for storing data for future reference.
Once the project is released while period end closing plan values are copied to version made for each period but user has performed transaction CJ9F and seleted target version wrong (instead of using Z01 he used 02). thus baseline budget values are overwritten.
Now i want to revert changes in version 02.
Hi...
if i got it correct the user copied plan cost/rev from version A to version B and now you need to revert to old values of version B.
As far as i know there is no straight way to do it..but if i could propose a workaround:
Multiply the plan values of version A with (-1): instead of cost element plan value 100 apply -100, and then copy this to version B. That would bring back the old values of version B.
Give it a try and let us know
Best Regards
Panagiotis
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
User | Count |
---|---|
90 | |
8 | |
7 | |
4 | |
4 | |
3 | |
3 | |
3 | |
3 | |
3 |
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.