on 03-13-2014 8:51 AM
Hi,
i want to carry forward budget next year for single wbs element.
pl suggest me.
Thanks & Regards
Purna.M
Hi,
Go to CJCO click on Dynamic Selection and in master data of WBS element select No of person responsible and give the person responsible and execute.before that maintain no of person responsible in that specific WBS element.
hope it will solve ur problem.
Regards
Avinash