SAP REFX Contract with multiple sub-contracts in a single contract.

Former Member
0 Kudos

Hi RE Experts,

I have one requirement in RE Contract. I have created sub-contract (like 600,601,603) and assigned them to main contracts (604) in General tab Main contract field I entered (Company code) and link to main contract 604. When I clicked icon - Display object list. I get RE80 screen. REC 100/604 Under Subordinate Objects I see all other contracts listed i.e 600,601,603.

My question is to run a report and see under main contract 604 all other sub-contracts list. But I could not run any report to see my requirement.

Is this best practise to assign multiple sub-contracts in a main single contract.

Any suggestions or advise what is the best practice to maintain.

Regards,
Suresh

Accepted Solutions (0)

Answers (1)

Answers (1)

former_member196871
Active Participant
0 Kudos

You can use the main contract-sub-contract assignment as per your business requirement.

You can use the report REISCN. select change layout button (Ctrl+F8) select the hidden field Main Contract to your layout and press copy. Now you can view all the contracts based on the main contract.