on 03-11-2014 9:45 AM
Hi,
I still don't know how you have changed the account assignment from one WBS to another in me22n.
Also, you are using non stock material (Item Category L) and Acct Assignment Category as N (Which is Network)
Anyways, my views on your issue is very simple. Actually, what I can see from your screen shot is that you have generated a PR and Reservation from PS initially by attaching material component to network activity. Afterwards, you have created PO with respect to PR.
Now, I don't think that you can assign the same PO to another WBS. Just think from accounting and logistic point of view. What will happen to commitment cost that is being already created/raised.?
I think what you need to do is just short close the commitment cost (means short close the PR and PO both) or simply delete this material component from cj20n and simultaneously keep track of commitment cost through CJI5 transaction code. After this, just simply attach a same material code to your new network activity which is under new WBS.
Then you will have your new PR and PO. I hope I am clear to you. But wait for other experts to comment on this.
Regards,
Amit Rajoria
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
firstly - item category is N and not L
secondly the status is CRTD - nothing to consider at this point
your argument was valid if the status was released and say partial posting was done etc and then change of PO assignment to another wbs element was attempted
that is not the case so all is well
As virendra said this seems to be PO - me22n ,if it be sales order - va02 .
find "account assignment " tab and change the WBS .
BE sure if its header level Sales order or WBS is assigned to any line item .
LEt me know ,if you got it.
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
It seems to be custom development and what i can predict is the PO is getting assigned to WBS and stored in ZTABLE and asiigning it to Purchase order.
But it is not getting changed when changing PO assignment. I suggest get in touch with technical team and ask them to update data displayed in CJ20N based on changes done In PO
Firstly this post refers to PO assignment to WBS and not sales order
You can change the assignment in the PO via ME22N
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
User | Count |
---|---|
101 | |
12 | |
11 | |
6 | |
6 | |
4 | |
3 | |
3 | |
3 | |
3 |
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.