We are running /sapapo/ts_lcm_reorg, however even after running for 7 hours the job did not complete.
We are running with option
1. check superfluous objects
2. Repair
3. Lock PI
Is there alternative using which we can improve the performance of the program as we cannot keep the planning version of production system locked for long periods.
Please suggest.
Thanks,
Sanjog Mishrikotkar
Hi Sanjog,
When you run the report /SAPAPO/TS_LCM_REORG, no other processes for a planning area (applies only to planning areas with key figures based on liveCache time series) should be allowed to run with the same planning version, since this would result in liveCache objects that are still required by the other parallel process being recognized as unnecessary (and then possibly deleted).
For this reason, SAP recommend that you always run the report with the option 'Lock planning version'.In this case, all planning areas that use the planning version to be checked are locked for the relevant version.If you cannot activate the lock, report execution is interrupted and a list of system users is displayed, showing users who have already set a change lock for the planning version.
Regards,
R.Brahmankar
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
User | Count |
---|---|
9 | |
4 | |
3 | |
2 | |
2 | |
1 | |
1 | |
1 | |
1 | |
1 |
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.