Long running /sapapo/TS_LCM_REORG

Former Member
0 Kudos


Hi,

We are running /sapapo/ts_lcm_reorg, however even after running for 7 hours the job did not complete.

We are running with option

1. check superfluous objects

2. Repair

3. Lock PI

Is there alternative using which we can improve the performance of the program as we cannot keep the planning version of production system locked for long periods.

Please suggest.

Thanks,

Sanjog Mishrikotkar

Accepted Solutions (0)

Answers (1)

Answers (1)

rupesh_brahmankar3
Active Contributor
0 Kudos

Hi Sanjog,

When you run the report /SAPAPO/TS_LCM_REORG, no other processes for a planning area (applies only to planning areas with key figures based on liveCache time series) should be allowed to run with the same planning version, since this would result in liveCache objects that are still required by the other parallel process being recognized as unnecessary (and then possibly deleted).

For this reason, SAP recommend that you always run the report with the option 'Lock planning version'.In this case, all planning areas that use the planning version to be checked are locked for the relevant version.If you cannot activate the lock, report execution is interrupted and a list of system users is displayed, showing users who have already set a change lock for the planning version.

Regards,

R.Brahmankar

Former Member
0 Kudos

Hi Rupesh,

Thanks for the response.

However as mentioned in my post we are already running the program with Planning version locked.

We are still facing the issue for long run time with this setting.

Thanks,

Sanjog Mishrikotkar