Hi All,
I want to HOLD the project but my WBS status profile is not assigned automatically for some old projects to WBS . Now I want to assign the HOLD status to project but due to Status profile was not assigned to WBS it creates PO , now just want to know if I assign it manually is their any effect to WBS
Thanks
Hi Virendra,
you can manually assign status profile to WBS.
In status profile you can configure different statuses and you can control various business transactions.
once you assign status profile to WBS element, User status gets activated as per your configuration.
You can set user status and stop creation of PO.
Hope this will help you.
Regards,
Sandeep
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
You can assign manually
Change in WBS status profile afterwards is not retrospective - means that old ones do not get changed
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
User | Count |
---|---|
108 | |
12 | |
11 | |
6 | |
5 | |
4 | |
3 | |
3 | |
3 | |
3 |
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.