Dear Gurus,
We have 3 quality labs and each lab is sent a separate samples to inspect certain characteristics once we receive material from production. I have created an inspection plan and mapped these three labs as work center in operation and then assigned MICs under each operation to inspect.
Now my issue is how to map separate 3 samples to inspection lot generated from production ( type-4) and also how to configure that to inspection plan.
I have to result record for all these three physical sample as withdrawn from Lot based upon inspection plan as mentioned above.
I can mention sample drawing procedure in inspection plan but how to map actual sample there.
Any help will be greatly appreciated.
Regards,
Satish
Hi Satish,
Use inspection points 100 in Quality Plan.
Go through the below link.
http://wiki.scn.sap.com/wiki/display/ERPLO/QM-PROD?original_fqdn=wiki.sdn.sap.com
Thanks & Regards,
Ramagiri
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Try inserting a partial sample number for each mic in each operation.
In operation one, use partial sample number 001.
In operation two, use partial sample number 002.
In operation three, use partial sample number 003.
Craig
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Thanks all. I am mapping system based upon suggestion from Gurus. Will close the thread soon .
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Hi Satish
You are creating three operation for depicting three testing Labs.
Against each lab (operation) you had assigned MICs as per your requirement.
Now you have to assign a SDP along with inspection point type 200 for physical sample in task list.
After prod confirmation system will create inspection lot along with a sample by default for 1st operation.
For other operations you have to create samples manually referring the same inspection lot (QPR6).Remember to click ' Create Insp points' and mention operation.
Release the samples in QPR4.
Now when you go for result recording system would ask first for operation, so select the operation , then system will ask for insp point (sample no).There click on assign insp point , so system will provide the Sample no which were created in QPR6 for that particular operation.
Please follow the steps and revert.
Regards
D Mohanty
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
User | Count |
---|---|
95 | |
11 | |
11 | |
6 | |
6 | |
4 | |
4 | |
3 | |
3 | |
3 |
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.