Hi Experts,

Need your help on using deployment/real time deployment using target stock level method for transfer between location types:

1.) 1007 to multiple 1007

2.) 1007 to multiple 1002

Can it be done & what enhancements would be required to do it?

Let me know if you require some more clarification on the above requirement.

Regards,

Vinay

Accepted Solutions (1)

Accepted Solutions (1)

Former Member
0 Kudos

Hi Guys,

Was able to achieve this scenario after i maintained MRP area as issuing storage location in location master storage location tab.

Thanks.

Regards,

Vinay

Answers (2)

Answers (2)

thamizhchelvan_gunasekara
Active Participant
0 Kudos

Hi,

Also refer the note

                         1328586  - Deployment to MRP Areas

BR

Thamizh

Former Member
0 Kudos

Thanks Thamizh

I was able to carry to carry out deployment from 1002 location to multiple 1007 locations using real time deployment with fair share.

I wasn't able to carry out deployment from 1007 locations to multiple 1007 locations. i am using PB 9ADRP_FSS.

1.) is it because MRP areas creates stock transfer reservation on source location , as per note i should be able to deploy on forecast/target stock level with real time deployment with MRP areas to MRP areas scenario.

2.) Basic question, will deployment work in this scenario 1007 to multiple 1007 ( with any technical modifications if not possible with standard systems).

Thanks again.

Regards,

Vinay

thamizhchelvan_gunasekara
Active Participant
0 Kudos

Hi Vinay,

Refer the below thread

http://scn.sap.com/thread/1585517


BR

Thamizh