on 03-07-2014 8:55 AM
Hi SPP Experts!
We do have the Trigger in SPP_Deployment for the following:
SPP_FR_CHANGED Change to Fixed Demands, Receipts
SPP_PICK_DENIAL Pick Denial
SPP_PULL_DEPLOYMENT Pull Deployment Trigger
SPP_REPL_INDI_CHANGE Replenishment Indicator Changed
SPP_STOCK_ADJUSTMENT Stock Change
SPP_WAREHOUSE_RESTR Location Product Locked by Storage
Is there any Trigger for CHANGE IN DEMAND. --(Normal demand like sales orders, Stock trnsfer order, forecast change, etc)
If we receive any demand at one child plant, today, that will become over due the next day,
then we expect a trigger should happen and in the deployment run, child plant should get the product from the Mother plant.
Please confirm, thanks
regards
SRS Kannan
SRS,
Well, I have never worked in SPP. However, it is possible through EDQA and/or ODL to have a change in Demand instantly trigger an event. I have been told that EDQA is supported in SPP.
Event-Driven Quantity Assignment (SCM-APO-ATP-EQA) - Functions of the Redistribution - SAP Library
Best Regards,
DB49
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
User | Count |
---|---|
8 | |
3 | |
2 | |
1 | |
1 | |
1 | |
1 | |
1 | |
1 | |
1 |
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.