on 03-07-2014 5:28 AM
Hi All,
I am facing a issue in project system where we have to double our budget, if we need to run a settlement in the system.
For a example, if we have a budget of 100,000 and that is allocated to TWO sub WBS Elements as 50,000 each and when we want to run the settlement run it informs us that the budget is exceeded. So if we need to get the settlement run we have to allocate additional budget to the main WBS Element. But when we checked all the Purchases for the respective WBS, we find that the budget is not exceeded, but the settlement is checking for budget again in the main WBS Element.
This is the way our consultants have configured this and now they are no more in the company. Can any one ex-plane how we can fix this so that we don't need to allocate more budget to the main WBS Element.
Regards
Ruchendra
Hi Ruchendra,
Have you checked the settlement rule ..It might be receiver as higher level wbs-element in lower level wbs-element.
For example:-
You maintained two 2nd level wbs-element below 1st level wbs with 50000 budget each.
Now you consumed budget and cost inc rued.
Now while settlement this cost moves to higher level wbs-elemnt bcoz of settlement rule.
Thats why it needs budget to cover up that cost.
Check this ..It might help you.
Thanks
Rahul
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Hi..
besides the info mentioned above ....it would be helpful to let us know of the settlement you are trying to execute (sender, receiver...)
BR
Panagiotis
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Hi,
Apart from above suggestions,
Execute tcode CJIC and check the columns Rem.val.cnt.cur. & Capitalized to AUC.
Rem.val.cnt.cur.: total actuals against a wbs
Capitalized to AUC: actuals, those have been capitalized on AUC
If in some line item, Rem.val.cnt.cur =X (some value) and Capitalized to AUC =0.0 then that X value needs to be capitalized on AUC.
Also run CJEN & CJBN before running settlement.
Regards
Shishir
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Hi Ruchendra,
Please execute report S_ALR_87013558 and look for assigned and available cost/budget.
Assigned cost will be a total of actual+commitment cost and commitment cost can be seen by CJI3 report.
By executing the above processes, you will be able to know how much your budget has been consumed against allocated budget which will surely give you a clear picture.
Regards,
Amit
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Hi Amit,
Sorry to bug you like this but that is not my question. Let me enplane to like this.
Main WBS = 100,000
Allocated this budget to TWO sub WBS Elements
SUB WBS 01 = 50,000
SUB WBS 02 = 50,000
so when you use the full budgets in both WBS Elements and execute the settlement run it says that the budget in Main WBS Element should be set as 200,000.
why is this? settlement run need 200,000 to settle the accounts. I need t know what is the issue in the logic that makes the system behave like this.
Regards
Ruchendra
Hi Ruchenrda,
Check first budget profile which combination they have maintianed i.e all type of trnascation or PR ,PO level and all then the budget report tables bpja,bpge
if everything is correct try allocate the budget CJ31
Regards,
Raman
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Hi Raman,
Thanks for the quick response.
I need to enplane, I dont want to allocate more budget to the Main WBS Element as I explained above, I have allocated the Budget in the main WBS element to the TWO sub WBS Elements. What I need to know is why I need to double the Budget in the Main WBS Element to complete the, settlement run.
I checked the Budget Profile in (SPRO -> Project System -> Costs -> Budget -> Maintain Budget Profiles) but I am unable to find any settings related to PO or PR. can you be more specific as I am totally new to this module.
Regards
Ruchendra
User | Count |
---|---|
108 | |
12 | |
11 | |
6 | |
5 | |
4 | |
3 | |
3 | |
3 | |
3 |
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.