on 03-07-2014 4:19 AM
Hello All,
I am facing one problem in updating cProject task using BAPI_BUS2175_CHANGE. I am using cProject 4.5 and carrying out following steps -
1. I am executing BAPI_BUS2175_CHANGE using test sequence.
2. I am Choosing FM BAPI_BUS2175_CHANGE at sequence 1 and FM BAPI_CPROJECTS_COMMIT_WORK at sequence 2
3. I Entered GUID number of the task for which Actual Finish Date is to be updated
4. In Import Parameters IS_TASK, I am entering "EN" in field "TASK_NAME_LANGUAGE" and actual finish date i.e. "06.03.2014" in field "ACTUAL_FINISH_DATE"
5. Then in Import Parameters IS_TASK_UPD, I am marking "X" in fields TASK_NAME_LANGUAGE and ACTUAL_FINISH_DATE
After execution of BAPI, I am getting following messages
I DPR_BAPI 157 BOR object Task '00000000000000006054': BAPI method CHANGE
W DPR_TASK 026 Duration of task is being adjusted - actual dates exist
W DPR_SHARED 246 Task subtask_4: Status "Released" - No automatic scheduling
S DPR_BAPI 113 Valid data is changed after saving successfully
Then I go back and save
But the Actual Finish Date does not get updated on task in cProject.
Request you to kindly provide me inputs on the same in case I am missing something or following some wrong sequence in BAPI
Thanks and Regards,
Mayur
Hello All,
Request your kind inputs on this...
We are stuck up here and not able to get through
Thanks in advance
Best Regards,
Mayur
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Hello Mayur?
Do you call this FM while running cProjects? Is it somewhere in the business logic? If so, you should know that it's advised not to use COMMIT WORK and just allow the standard Save functionality.
The reason behind is:
1. You update your data and commit it to the database. (This is alright outside cProjects).
2. But then in the load project you already have the old data. So when you press the Save button, this will overwrite the entries you already save in the DB.
I hope I got it right... maybe you can provide some more details.
Tudor
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Hi Tudor,
Thanks for your reply,
I am trying to update Actual Finish Date on existing tasks available in projects of cProject.
But when I execute the BAPI, project was not open on any of the screen. Even messages I am receiving during the execution specify successful updation of task.
But when I press the save button, results does not get updated in tables
Best Regards,
Mayur