Hi Guys

After renaming a test Solution Manager, which is a copy from an existing System, Change Management Tab is not visible in the a Project Attributes.

Before the SID renaming, the tab was visible, but after chaning the name to SMT, it no longer appear.

When accessing  SOLAR_PROJECT_ADMIN transaction, under System Landscape, there are only three tabs instead of four

Some logical relation is missing? Any idea where can I verify why?

Thanks!

Copied and Renamed system (SMT) with SOLMAN_ADMIN, client 200

Original System (SSM), user SOLMAN_ADMIN on Client 200

Accepted Solutions (1)

Accepted Solutions (1)

raquel_pereiradacunha
Active Contributor
0 Kudos

Hi,

as you copied the system, probably there is a missing entry which defines the client in which ChaRM will be active. Check in SPRO below "Change Management->Basic Configuration" the IMG activity "Activate Integration with Change Request Management->Activate Change Request Management and Set-up client". It must have your client 200 specified.

Regards,

Raquel

former_member229542
Active Participant
0 Kudos

Thanks Raquel, indeed i verified that on SPRO, and now the tab is showing up in Project Administration

Thanks for your quick response!

former_member228464
Participant
0 Kudos

Thanks, worked for me too... Cheer!!!