on 03-06-2014 9:44 AM
Dear ,,
i have 20 plants but STO Process is done only in 5 plants now i want to check in which plants STO Process is involved
Thanks a lot
Hi Amith,
Under the path,
IMG-->MATERIAL MANAGEMENT-->PURCHASING-->PURCHASE ORDER-->SET UP STOCK TRANSPORT ORDER
you can find the settings for
1. Create shipping data for Plants
2. Assign delivery type , one-step procedure , under delivery tolerance
if those settings are available for plants then you can enusre STO is enabled for that plant
try and revert
regards,
santosh
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
hello,
I am not very sure if you can search any table for STO. If you see there is an item cat for an STO as well (U as standard) however it comes as a structure, so you will not be able to find it in EKPO table as well. EKKO does has the supplying plant, but on condition that at least one documents had to created in all of your 5 plants.
However SAP has provided some standard reports ME2W.
Run this report with all the plants available for as supplying plants. I hope you will get your required plants which are responsible for STO.
N:B: Santosh is correct, i am not sure why you dont like his answer but want to search a table.
regards,
Sayantan