on 03-01-2014 10:09 AM
In the Production version in ECC there are 2 operations having same work center.
After CIF, in PPM , work center is getting assigned to only in first operation and missing in 2nd operation.
Any one tell me what is wrong ?
thakns
ukumar
Hello ukumar,
Please try deleting the PPM and Plan from APO and then retransferring it to APO. You can do RIMODINI, this may help you.
Thank you
Satish Waghmare