Hi,
We have the requirement to find an option to do a mass update of project staffing when a resource leaves & is replaced by another.
Scenario :
PM (A) is staffed as Program Manager on 50 active projects,is the responsible resource for these projects & has left the company
PM (B) is replacing PM (A) and needs to be staffed as program manager for the 50 active projects & become the responsible resource.
PM (A) should be removed from the 50 projects or made inactive.
As you can imagine to do this manually for each project is very time consuming.
We would like to know if there is any mass update function to achieve the above scenario.
Kind Regards,
Alison.
Hi Alison,
please see SAP Note
1624101 - Replace user/resource (resource)
Functionality is available with SP07 for 5.0, but it has to be switched on. The note
explains how to do it.
Kind regards,
Florian
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
User | Count |
---|---|
10 | |
5 | |
1 | |
1 | |
1 | |
1 | |
1 | |
1 | |
1 | |
1 |
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.