on 02-26-2014 10:59 AM
Hello,
We have a scenario, where we are creating Multiple Production versions which CIF to APO with Multiple PDS. In multiple PV different work centers & different BOM has been assigned… We want to do Capacity planning for all Source of Supply.
I see only option is to use SAP_REM heuristic…But we don’t want to use this heuristic, as it is having lots of restriction…
I have tried with SAP PP heuristic for creating planned orders, and then doing capacity planning using SAP_DS_02…Enhanced Backward scheduling & SAP_DS_01 Stable Forward Scheduling … But it is still doesn't select the alternative source of supply…
Is there any heuristic, or running multiple sequence of heuristic which can plan on multiple PDS for capacity leveling …..
Regards
Debashis
Hi Debhashis
Could you please share the solution ?
As per my knowledge this can be done by :
During planning, the system selects the source of supply according to the
following criteria:
Quota arrangements: If the quota arrangement heuristic SAP_PP_Q001 is defined
in the product master, quota arrangements are taken into consideration.
Priority (highest priority = 0): If several sources of supply can deliver on time, the
source of supply with the highest priority is selected.
Costs: If there are several sources of supply with the same priority, the most
cost-effective option is selected.
Adherence to delivery dates: A source of supply that can deliver the required
quantity on time is always used in the production planning run. If the source of
supply selected on the basis of quota arrangement, priority and costs cannot meet
the delivery date for the product, the system selects the next best procurement
alternative in terms of quota arrangement, priority and costs, and checks whether
this source of supply ensures that the delivery dates can be met. Adherence to
delivery dates is therefore a hard condition. If none of the available procurement
alternatives can meet the due date, the order is created at a later date (the
alternative with the smallest delay is selected).
Regards
Rami
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Hii Rami,
We have done custom modification to some of function modules, and applied to the optimizer.
PPDS standard Optimizer does not move orders from one source of supply to another supply. It just moves orders from one Mode to different Mode in the PDS.
Where as we have done such modification, that optimizer call all the source supply and consider them as a different dummy Mode priority and moved the orders as per the weightage we have selected in optimizer profile(set up time, delay time, delay cost etc).
Regards
Debashis
Hi Debashis
I don't know whether you talk about PPDS heuristic or PPDS Optimizer
PPDS Optimizer move the order to others source of supply according to priorities ,please check SAP OSS FAQ note 1374824 FAQ - Order Creation PP/DS Optimization
Q13: How are Source of Supply priorities picked?
A13: Using the Procurement Priority in the header of the PPM or PDS.
Thanks
Regards
Hii Rami,
PPDS Optimizer, does consider source of supply Priorities, Bit it can;t move order from one source to others.
PPDS optmizer can move order from one mode priority to other mode priority with in a single source of supply ..
example : We run optimizer as resource as a selection and there are two resource . We do have two PDS for the below combination
PDS 1 : mat 1 , Resource 1 , Bom 1 (procurement priority 0)
PDS 2 : Mat 1 , resource 2, Bom 1 (Procurement priority 1)
Optimizer won';t be able to move order s from PDS 1 to PDS2 ..
Optimizer can move order if it is the below scenario:
PDS1 with Mode A: mat 1 , Resource 1 , Bom 1
PDS 1 with Mode B : mat 1 , Resource 2 , Bom 1..
Hope i have answered your query...
Regards
Debashis
Hi Debasis,
I think this can be handled in two steps ,
1) If you have multiple production versions due to different BOM the production version selection can be made based on lot size criteria, in PP heuristic. As source of supply selection happens in PP.
2) To drill down to all alternate resources you can use alternate resources within same master recipe , create same classification for alternate resources and attach to all master recipe. Detailed scheduling strategy will take care of alternate resources with in same PDS. you just need to select option "consider alternate modes" in DS strategy. This will allow you to level capacity on all the alternate resources. This works well. As far as i know any DS heuristic will not change source of supply , so this can be handled using alternate resources.
I hope this helps you.
Regards,
Dharmesh
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Hii Dharmesh,
Thanks for your reply, But we can't use option one..
1. We use different PV for different BOM components, and it can be used for same lot size...
Now for option 2
2. We are already using classification for alternative resources, which moves as alternative modes into PDS. There is no issue,But certain cases , we have different speed of machines , for them we have to create another routing and another PV. there we got into stuck..
any other solution for this , specially for different routing with one PDS... So that we can move them alternative modes...
Regards
Debashis
Hi Debhashis,
It might be possible technically , but you will not be able to know how much work you will end up doing. If your technical resource can replicate Function module used in SAP_MULT_SCH in EPH1. But i can not not be sure about all the touch points inside function module. This is like creating a new heuristic. You can give a try. Cant you propose your client for EHP2 upgrade if requirement is very firm , there are other additional features as well in EHP2.
Regards,
Dharmesh.Gohel.
Hi Debashis,
I don't think any heuristic will help you in this case. As I know optimizer can do that with resource network. For heuristic you need to do some Enhancement with custom coding by using BADI /SAPAPO/RRP_SRC_EXIT where you can redetermine the source of supply as alternate PDS.
Have a look on OSS note 449263 - User exit: Alternative sources of supply not checked in MRP.
Regards,
R.Brahmankar
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Hii Rupesh,
Thanks for ur reply, Even i think so, and we are also designing the same customized optimizer to move orders into different source of supply..
But this is taking a lot of time for testing and developing....So just curious is there any other solution to just create a finite planning taking alternative source of supply into considerations...
if you have some alternative solution please share ...
Regards
Debashis
User | Count |
---|---|
8 | |
4 | |
3 | |
2 | |
2 | |
1 | |
1 | |
1 | |
1 | |
1 |
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.