on 02-26-2014 10:56 AM
Hi Experts,
I have one clarification on put away
I have a set of bin as below and is there a way I can say to picker to go in a specific sequence as per the priority assigned.
This is to achieve the optimal picking sequence for the picker. Or is there any specific way to achieve the same.
Bin | Priority |
A-002 | 2 |
A-003 | 4 |
A-001 | 5 |
B-001 | 1 |
Kindly reply back at the earliest.
Regards
Manish
Dear All,
Please throw some light on this issue. I'm reading the threads but no concrete answer for this.
Will sort profiles help in sorting the items in the TO while creating (not printing) in the desired way.
Whole objective is to sort the bins as needed while creating TO (LT03).
Regards
Manish
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Dear All,
Kindly give your inputs. I have tried searching but could not get specifically this issue's answer.
Regards
Manish
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
did you search in help.sap.com ? e.g. Define Sort Sequence for Stock Removal (Picking) (SAP Library - Warehouse Management)
Hi Jurgen,
I'm using picking strategy as "F" - FIFO. Below is my bin template and structure
Template | ACNNCNNCCC |
Structure | A BB CC |
Below is my sort sequence for put away and picking. Put away is working fine but not picking
Sort Seq Putaway | Rack A | Sort Seq Picking |
0205 | A-02-05 | A02 |
0204 | A-02-04 | A02 |
0203 | A-02-03 | A02 |
0202 | A-02-02 | A02 |
0201 | A-02-01 | A02 |
0105 | A-01-05 | A01 |
0104 | A-01-04 | A01 |
0103 | A-01-03 | A01 |
0102 | A-01-02 | A01 |
0101 | A-01-01 | A01 |
Putaway sequence is working properly as below. But picking is also happening the same way. We want the picking to happen for the first Rack "A" and the it should go level 1 & 2 and then to second rack "B" so on.. Please confirm if my sort sequence correct for picking.
1st fill | A-01-01 | B-01-01 | C-01-01 |
--> | |||
2nd fill | A-01-02 | B-01-02 | C-01-02 |
--> | |||
3rd fill | XX | B-01-03 | C-01-03 |
--> | |||
4th fill | A-01-04 | B-01-04 |
Regards
Manish
Hi Jurgen,
Thanks for the reply.
I'm clear on sort sequence and it is working on the putaway perfectly. The problem I'm facing is in picking. The same sequence is not working in picking. I found one of your another post and it was helpful. I understood that first the strategy will work (either FIFO / Partial Quantities) then the sequencing will happen.
I have changed my strategy from "F" to "A" (part quantities). Still the bins are not getting sequenced in TO. I have attached the screen shots of the same. Please let me know if I'm missing some concept / configuration.
Regards
Manish
User | Count |
---|---|
108 | |
12 | |
11 | |
6 | |
5 | |
4 | |
3 | |
3 | |
3 | |
3 |