Hello everyone
One particular error is troubling me a lot. While CIFing PDS from ECC to APO, an error comes which says- "operation XXXXXX has minimum interval time > maximum interval time".
Had it been, only one case, we would have ignored. But there are plenty and I dont know which place to look into in order to solve this.
In APO, I found the PLPO tables where minimum & maximum interval time are present but still it doesn't reveal the PDS number.
Kindly help.
Soumyajit
Hi Soumyait,
In PLPO you will get the Group and Counter. Enter that group in CA03 or C203 select counter here you will get the product and operation which defined for wait and queue time.
In master recipe predecessor relationship will have the
minimum time interval
maximum time interval
Regards,
R.Brahmankar
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
User | Count |
---|---|
8 | |
4 | |
3 | |
2 | |
2 | |
1 | |
1 | |
1 | |
1 | |
1 |
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.