on 02-24-2014 2:00 PM
Hi All,
I have been investigating posting statistical costs via transaction KAFD onto a WBS. I have noticed however that these statistical costs are not subject to Availability Control. My questions are:
1 - Is this std SAP behaviour?
2 - How to switch AVAC on to consider statistical postings?
Thanks,
Werner
Hi,
if you post statistical costs in KAFD they consume budget ( amount is budget assigned), but it is true that there is not AVAC.
if you need AVAC you can try to write line items for this statistical costs( not sure if writting line items the AVAC is checked)
regards
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Hi,
Wherever you use WBS as account assignment element, the AVAC will work if you have activated AVAC. This is system's standard behavior.
Activate AVAC- CJBV
Deactivate AVAC- CJBW
Note: Don't for get to execute CJBN(Reconstruct AVAC) after activation or deactivation of AVAC.
Regards
Shishir
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
User | Count |
---|---|
100 | |
11 | |
10 | |
6 | |
6 | |
5 | |
4 | |
4 | |
3 | |
3 |
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.