on 03-20-2007 5:13 AM
This is the requirement I have
Create a new field under Project Definition. This field, which will show a numeric value, should always be in display mode. This value is a result of a calculation. The calculation will depend on the values in the fields "Task completion %", "Planned hours for the task" and the "Status of the Phase". The said calculation will have to be written using ABAP code, I suppose.
I know how to create a new field under Project Definition and make it in display mode.
I would like to know the following --- <b>Where do we write the ABAP coding</b> ?
Regards,
R. Rajesh Kumar
Hi Rajesh
Check the BAdI: DPR_ATTRIBUTES
Regards,
Reema.
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Hi Rajesh,
Would you please let me known, which cProject release(4.0 or 3.1) do you use?
Kind regards,
Zhenbo
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.