cancel
Showing results for 
Search instead for 
Did you mean: 

Interrupt operation in planning board

former_member691361
Participant
0 Kudos

Hi,

We are doing the interruption of an operation to rescheule the order.

After doing the final confirmation of the operation also the interrpted operation is not getting moved from the planning board but the remaining orders are moved while doing final confirmation.What is the process of removing the interrupted operation from planning board?

While doing interruption should we do for the particular operation or for the entire process order.

Thanks,

Prash

Accepted Solutions (1)

Accepted Solutions (1)

rupesh_brahmankar3
Active Contributor
0 Kudos

Hi Prash,

You can do the interruption for operation or for the entire process order also.

This issue is address in OSS note  1670887 - Wrong final confirmation for interrupted operations

Regard,

R.Brahmankar

former_member691361
Participant
0 Kudos

Thanks Rupesh. The note helped me.

Thanks,

Prash

rupesh_brahmankar3
Active Contributor
0 Kudos

Hi Prashanth,

That's great..!! Please close the discussion.

Regards,

R.Brahmankar

Answers (1)

Answers (1)

former_member691361
Participant
0 Kudos

Hi,

Any updates on this please?

How the process of confirmation has to be carried out for interrupted operation?

Thanks,

Prash