on 02-19-2014 12:19 PM
Hi,
We are doing the interruption of an operation to rescheule the order.
After doing the final confirmation of the operation also the interrpted operation is not getting moved from the planning board but the remaining orders are moved while doing final confirmation.What is the process of removing the interrupted operation from planning board?
While doing interruption should we do for the particular operation or for the entire process order.
Thanks,
Prash
Hi Prash,
You can do the interruption for operation or for the entire process order also.
This issue is address in OSS note 1670887 - Wrong final confirmation for interrupted operations
Regard,
R.Brahmankar
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Hi,
Any updates on this please?
How the process of confirmation has to be carried out for interrupted operation?
Thanks,
Prash
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
User | Count |
---|---|
8 | |
4 | |
3 | |
2 | |
2 | |
1 | |
1 | |
1 | |
1 | |
1 |
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.