on 02-17-2014 4:04 PM
Hi'
In CMP2/CMP3 we allocate/plan employees to PS-activities - with specific hours per day/week.
In CAT2 the employees create confirmations of their actual hours spend at the activities.
We would like to have a report where the Project Manager can see the planned versus actual hours spend per employee.
We could build a report by informations in the database tables from CMP2/CMP3 and CAT2/PS confirmation. But - the problem is, that when an activity get status Tecnically completed or Closed - then the CMP2/CMP3 informations are deleted from the database tables and can no longer be used.
I hope someone has faced same request, have solved the challenge and would kindly share the solution with me.
Best regards
Lone würtz
Dear CCS team,
note for workings consider one activity type is one personal resource.
rate of per hour for person is maintained in activity type
with this considerations you can create six resources for one work center
when you create a single activity you can assign one work center with acitvity type and then assign the same resource in the person assignment,(work or duration can be calculated if either one is known)this work stands for one resource. thisis planned
when you confirm from HT through CAT2 and CATA, transfer it to PS, actual work is displayed
if you require more than one activity you can go for activity elements where in you can create n number of personnel resource,under one activity as per requirement
check report CN41N,create your layout with following columns
Identification,:if hierarchy is expanded you shall find the work center along with person resource number in identification against which work and actual work are assigned
actual work
work
date columns as per reuqirements
tentative work
duration
actual costs
As per requirement select the columns
hope this shall solve your query
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Dear Sushrut Sheth
Thank you for your input
We have around 3000 employees. Today every employee can use 5-25 Activity types.
A Network activity usually have 5-50 employees
The necessary master data of activity types and Network activities/Activity elements are going to be unmanageable for us with the proposed solution.
In addition you can still not use the functionality of CMP2/CMP3 to manually divide the planned hours per employee per period (e.g. day/week/month).
As far as I can see we have to replicate the tables KBED, KBEZ and KPER with the planned data, update for every change, but not delete the records when status TECO/CLSD is set at the network activity.
In that way we can keep the planned hours per employee and compare with the actual data.
I have hoped someone had found a smart solution for the topic
Further input would be appreciated.
Best regards
Lone
Thanks!
CMP9 show planned values, but not actual.
My first plan was to see if it is possible to add actual values to CMP9.
But - CMP9 should read in the Z-tables instead of the original tables => we should copy to a ZCMP9 anyway. And this report is not as flexible as e.g. CATS_DA...
Maybe is is easier to add planned values to a ZCATS_DA-report - or create a totally new report.
I still hope for inputs until I can have the ABAP-resources necessary to develop a solution
Best regards
Lone
Please check report CN41
in this report select the required fields related to work,all the details are displayed in this report.no need to go to z reports or new table when you get the report with layout selection.
check it it shall work
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
have you looked at selecting actuals from COVP where awtyp = CATS
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Hi'
No I havent looked into COVP.
What is the benefit to use COVP instead of AFRU?
I still miss the planned values when the project has status TECO/CLSD - can someone help me solve that problem? Is the planned values from KBED/KBEZ/KPER created in other tables when deleted in these tables?
Regards
Lone
Hi,
As I know, when an activity gets reverse status from TECO/CLSD to REL, then the CMP2 information get deleted. Check the current status again.
Also try reconstructing project info database using tranx. CJEN and check again. May be come data inconsistency there.
Regards
Shishir
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Hi'
The CMP2/3 informations of planned hours are stored inat least 3 tables - KBED, KBEZ and KPER.
When status TECO/CLSD are given at an activity the entries in these tables are deleted. If you reverse TECO/CLSD to REL the data are not recreated. (And if they did it was not helpful enough, because we would (of course) like to be able to report and analyze historic data to learn form earlier projects which are now closed).
CJEN does not change this behavior.
I have not been able to find a SAP Standard report of planned/actual hours per employee per PS-activity - I suppose it is because the data are not avaliable in the full life-cycle of a project.
If you have found or constructed a report and have identified that records deleted from the K-tables are stored in other tables or a good solution of how to construct this by Z-tables, I would be happy to receive specific information
Regards
Lone
Hi'
Thank you for your answer.
AFRU contains all confirmations - but does it also contain planned values from the CMP-transactions?
It is not the planned value in field "Work" at the activity Im interested in. It is the planned values per person from the CMP-transactions I would like to have in a report together with the confirmations (from CATSDB/AFRU).
If you have already a report with these values - Im very interested to know from which tables the planned values per person is read
Best regards
Lone
HI CSS.....
For your query you need to make relationship between tables
activity table AFVC where you will get hours and activity number, ID number(for relationship).
KBED table for main capacity,
KBEZ, KPER, for split and person assignment of each period.respectively
you can compare data with AFRU table(actual confirmation table)
check note for 542941 for same.
Thanks
Rahul
Hi Rahul,
As I wrote earlier I have already found the tables KBED, KBEZ and KPER (and can join with AFRU).
But when status TECO or CLSD is set, the planned hours per employee is deleted from these tables. (And the records are not re-created is the status is reverted).
How have you solved this problem? Do you never close the projects?
Regards
Lone
User | Count |
---|---|
93 | |
11 | |
11 | |
6 | |
6 | |
4 | |
3 | |
3 | |
3 | |
3 |
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.