Non – Valuated Stock on WBS Level

Former Member

On Project Definition level the indicator is set for “No Project Stock” to control the project hierarchy.

Question, I only wants one WBS Elementto to be active for “Non – Valuated Stock” on  spares, Example QTY 1, value 0 and the full value amount is capitalized on the asset register.

Accepted Solutions (0)

Answers (1)

Answers (1)

former_member209919
Active Contributor
0 Kudos

HI Hannes,

SYstem manages project stock at project level not at WBS level, then all WBS in the project have to have the same setttings ( and they are defined at project level). If you need one WBS ( non valuate project stock) and the others with ( non project stock) you need to create different projects.