Hi There,

We copied TPV from 01 - Germany to use for country XX (for which SAP standard TPV not provided)

Now for additional destinations entered in trip the per diem for meals are not getting calculated.

when we raised it to SAP.

- SAP says - you should have copied from TPV 99 and not from 01

but now for single reason I cannot start from scratch.

Please help how to proceed.

Jay..

Accepted Solutions (0)

Answers (1)

Answers (1)

Former Member
0 Kudos

Dear Jaydeep,

We should not copy the variant 01 for which SAP not delivered the standard variants.

SAP mentioned already copy 99 variant for those country variants not delivered.

There is no way of to retain your configuration and change the variant now. Again need to develop from scratch.

Thanks & Regards,

Y.V.P.Deepak

Anwar20
Active Participant
0 Kudos

Hi Jaydeep Jadhav

As deepak said, You need to copy trip provision variant from International-99 . Once  you copied from 99. all the setting along with configuration table will get copied.

Now , you can make change as per your client business need.

As you have copied from 01.  now you have make change in goal setting  along with travel exp types . for impt, you need to make change in expert view table(V_T702N_A).

Hope it will help you.

Thanks