ZP05 is showing a WIP variation of xxx amount in January'14 on Project ABC. Normally this xxx amount should be posted into FI through CJ8G
Hi,
Please elaborate your query. I think ZP05 is custom trax. Please check this report with help of your ABAPer.
Regards
Shishir
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Hi,
Please discuss with your local PS expert again. As I know, ZP05 is not a standard SAP transaction.
For understanding WIP calculation, go through the links
http://scn.sap.com/docs/DOC-35712
Regards
Shishir
Thanks Shishir... we got it solved.
Acutually they had done settlement twice. I took the total amount and calculated the difference of it which gave the diffference amount of WIP variation in ZP05.
It was not the problem with Zp05, was problem with mismatch in the amount in ZP05 and the FI posting done from CJ8G.
Ritu
User | Count |
---|---|
89 | |
8 | |
7 | |
4 | |
4 | |
3 | |
3 | |
3 | |
3 | |
3 |
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.