Activity Confirmation Issue

Former Member
0 Kudos


Hi All,

I have an another query,

Let say i have an activity and also underlying activity elements in a network,

Now i will not confirm any of the activity elements in the network,but if i confirm the main activity is there any setting to let the user know that there are activity elements inside the activity which i am confirming.

may be like a warning message saying that "Activity elements are existing in the activity which are not confirmed"

Please write to me and let me know the answer as soon as possible.

Accepted Solutions (0)

Answers (1)

Answers (1)

Former Member
0 Kudos

Hi,

Why don't you just enter the network number at CN25 and let the system come up with its associated activity and its associated activity elements.

So when you press enter after putting the credential as only network number then system will bring you to next screen and there you can choose that you want to confirm activity or activity elements.

Is that not enough for you?

Regards,

Amit Rajoria