on 03-19-2007 1:50 PM
Hi
Can anyone help me write a macro to move the demand from the previous bucket to the current bucket?
The requirement as weeks passes by, the demand of the past week(if not met), should meet to the current bucket. The current bucket should hence show the total of the demand of the previous weeks and the current week. Hence of the demand of the current month is released in the 3rd week, the SNP planning book show accumulated demand of the previous 2 weeks in the 3rd week, in addition to the demand of the 3rd week.
TIA.
Hai,
We have acheived this requirement in our case as follows:
1. We are using Forecast (additional) key figure (FC) for this purpose.
2. Every week, we execute the copy backlog macro, which makes the key figure FC=0 and copies the backlog (unconsumed) forecast in key figure FA in the initial column.
3. Macro:
Delete FC in the initial: Forecast (additional)=0
Forecast (additional) in the current bucket =
Forecast (from initial)
Hope this helps you.
Regards,
Murali.J
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Hai,
I am giveing you the steps of the macro:
- Macro -> Right click: Add Macro -> Give description for the macro, settings for execution: Detls only
- Step 1: Add backlog in current bucket: -> User defined processing area:-> From period: Initial To period: Initial, Iterations: 1, Missing values: replace with 0, Processing direction: In future
Row: Forecast (additional): Column start: first current bucket =
Row: Forecast column start: Initial
- Step 2: Delete backlog FC in the initial column -> From period: Initial, To period: Initial, Iterations: 1
Row: Forecast (additional): Column start: Initial =
Operator/Function "0"
Hope this helps you,
Regards,
Murali.J
User | Count |
---|---|
8 | |
3 | |
2 | |
1 | |
1 | |
1 | |
1 | |
1 | |
1 | |
1 |
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.