Creation of work orders for multiple locations in mainteance items

Former Member
0 Kudos


Hi PM Experts,

I am working on sceanrio of mainteance planning for multiple functional locations. We have multiple functional locations with same task list operations and same planning schedule. I created a mainteance item for multiple locations with mainteance plan. When I schedule a mainteance plan, system creates one work for all locations listed in mainteance plan. Our business requirement is to create a seperate work orders for each location listed in mainteance plan.

Can this be acheived by standard configuration or do we need to use some user exit for this?

Thanks

Nilesh

Accepted Solutions (0)

Answers (1)

Answers (1)

Former Member
0 Kudos

Hope you created separate Maintenance Item for each location & assigned to one Maintenance Plan. If so, PM Orders will be generated separately for each location.

If you have assigned those locations in Object list of single Maintenance item, then only one PM order will be generated by having all locations in PM order object list.

In SAP, one Maintenance Item = one Maintenance order.