When we create PO, in some cases the statistical delivery date will appear in the PO whereas in most of the cases, it doesn't.
Can anyone please advise how we can enable the statistical delivery date in the PO ??? Do i need to raise the ticket ???
Looking forward to your valuable remarks
Regards,
Talha
Thissounds like an MM-PO related issue .. you most likely will get more replies if you post it in that forum. This forum relates to the SAP Sourcing/CLM application.
Thanks
Prasad
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Hi,
The statistical delivery date is basically used for vendor evaluation. It is changed along synchronous with the delivery date, if you have not yet outputted the order. After the output, the statistical delivery date will not change automatically with a delivery date change.
you have to maintain planned delivery days in the material master or info record planned delivery time
If you maintain delivery date,then system automatically insert date in the statiscal delivery date.
With Regards,
Jaheer
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.