Hi colleagues, do you know if SAP ME supports Variant Configuration scenarios from ERP?
Do you know where can I find information regarding it?
Thanks,
Wendell Moreira
Hi colleagues, thanks a lot!
But I have one more question regarding this:
On ERP side (PP), when we have a change in the configuration, PP has a functionality called OCM (Order Change Management), that identify the configuration changes, and make the changes.
How does it work with SAP ME? Do you know?
Many thanks,
Really appreciate,
Wendell Moreira
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Hello,
When your Production Order changes on ECC side, you just resend it to ME and it should update its records with new information either automatically, or in case SFCs are already released to production ME will put shop order on hold and send a message to responsible person to apply changes manually.
Regards,
Konstantin
Hi,
The automation of change replication is implemented within a scope of Data Replication Framework (DRF). For detials, see here:
SAPMEINT: SAP ERP Configuration - SAP Manufacturing Execution (SAP ME) - SAP Library
SAP Note 1555198
Regards,
Sergiy
Hi,
Depending on what is meant by Variant Configuration. By default there are no such thing (oe with similar name) in ME. If you can elaborate and explain more, maybe you could more specific answer.
Regards,
Konstantin
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Hi,
In typical variant configuration, Configuratble material will have super BOM and super Routing and exact routing and BOM for the production order will be determined based on characteristics chosen using object dependency function.
I think the question is about how would one interface super BOM or super Routing to ME as master data and subsequent production order with production order BOM and routing which is a subset of the super BOM and super routing. Will the object dependency also gets interfaced as conditional routing so that when the production order is interfaced ME would use right sets of operations which is applicable for the chosen set of characteristics
Regards
V. Divakar
Hello,
You don't transfer variant configuration master data (super BOM, super Routing) to ME.
When you transfer a production order to ME, it will contain the corresponding BOM and Routing; ME will create the production order + production order BOM + production order Routing. Where the production order BOM/Routing are a subset of the super BOM/Routing.
Best Regards,
Miguel
User | Count |
---|---|
108 | |
12 | |
11 | |
6 | |
5 | |
4 | |
3 | |
3 | |
3 | |
3 |
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.