Hi Team,
I would like to know if it is possible to do resource constraint project scheduling in Project systems. If yes does it use Genetic algorithms or any other heuristic to perform this.
Thanks,
Diana
Hi Diana,
I am not 100 percent sure, what you mean with 'Resource constraint project scheduling', but the Project scheduling does not take the resource into account.
Details Consulting note 151551 (network scheduling) and 683940 (WBS scheduling).
Simplified speaking, the project scheduling uses the data of activity and WBS. After the scheduling is done, the sub elements (activity element, material requirment dates, milestone, assignment of person) get determined.
There is function to allow plan the activity dates according the resource capacity. It is done manually, as far as I known.
Kind regards,
Zhenbo
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Agree with Wang. In scheduling of project, dates are come into point in SAP PS. Resource can't be schedule. But It can be plan.
If you are saying about resource planning then just search in the forum. there are a lot of discussions have already done.
Also go thru the link:
http://help.sap.com/saphelp_cpro31/helpdata/en/e8/00c73c52aacf5be10000000a114084/content.htm
Regards
Shishir
User | Count |
---|---|
108 | |
12 | |
11 | |
6 | |
5 | |
4 | |
3 | |
3 | |
3 | |
3 |
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.