on 02-10-2014 2:51 PM
Hello,
We use a specif program for PP.
The cancellation of a confirmation of production order doesn't trigger the creation of the order reservation in APO.
To get it, we have to change a date in the production order via CO02.
Do you have a workaround to avoid this?
Thank you.
Carica
Hi Catherine,
In R/3, generate and activate integration models with manual reservations.
Also you can use the Program - RCIFORDER_RESERVATIONS_COMPARE to compare the reservation in ECC and APO. Also you can reconcile the error. You can schedule this program background.
Please refer OSS note 538111 - Compare and reconcile production order reservations.
Regards,
R.Brahmankar
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Hi,
Thank you for your workaround. I've already seen it and indeed it works.
This can be helpful.
Anyway, I would like to understand why during this way of production reservations' creation, the event to update APO is not triggered.
In fact, after investigation, it seems that an update of the production order especially on date/qty data is needed....but not logical for me.
BR
Cathy