OrdRes(W) not created

0 Kudos

Hello,

We use a specif program for PP.

The cancellation of a confirmation of production order doesn't trigger the creation of the order reservation in APO.

To get it, we have to change a date in the production order via CO02.

Do you have a workaround to avoid this?

Thank you.

Carica

Accepted Solutions (1)

Accepted Solutions (1)

rupesh_brahmankar3
Active Contributor
0 Kudos

Hi Catherine,

In R/3, generate and activate integration models with manual reservations.

Also you  can use the Program  - RCIFORDER_RESERVATIONS_COMPARE to compare the reservation in ECC and APO. Also you can reconcile the error. You can schedule this program background.

Please refer OSS note  538111 - Compare and reconcile production order reservations.

Regards,

R.Brahmankar

0 Kudos

Hi,

Thank you for your workaround. I've already seen it and indeed it works.

This can be helpful.

Anyway, I would like to understand why during this way of production reservations' creation, the event to update APO is not triggered.

In fact, after investigation, it seems that an update of the production order especially on date/qty data is needed....but not logical for me.

BR

Cathy

rupesh_brahmankar3
Active Contributor
0 Kudos

Hi Catherine,

In R/3 Do you have activated integration models with manual reservations?

Apart from that you can schedule the Program  - RCIFORDER_RESERVATIONS_COMPARE in background for frequent  interval. to clear these inconsistencies.

Regards,

R.Brahmankar

0 Kudos

Hi,

Yes, I well checked manual reservations in IM.

I'm going to schedule the pgm RCIFORDER_RESERVATIONS_COMPARE.

Thank you for your collaboration.

Best regards

Cathy