Change Management remove 'finished projects' from selection list

kenny_vandemoortele
Participant
0 Kudos

Hi experts,

Is there a way to hide all our completed projects in our selection menu from Change Management.

for example in the screenshot below: project 10MR1 is completed (all Q-gates are set to 'passed', and the status of the project is set from 'new' to 'finished, 100%')

I hoped our list would become smaller, but all projects are still shown. We also know we can use filters but we would like to have a proper way to achieve this.

Thanks!

Regards,

Kenny

Accepted Solutions (0)

Answers (1)

Answers (1)

kenny_vandemoortele
Participant
0 Kudos

Allright, found it after some digging. Thanks anyway