Mitigation Control ID creation Error in GRC AC 10.0

Former Member
0 Kudos

Dear GRC Team,

While creating Mitigation Control ID i am getting error like ‘Valid-to’ date cannot be later than that of the parent Object.

I maintained all the Details in GENERAL Tab and click next Tab Access Risk then i am getting attached error.

I appreciate swift response.

Regards,

Rupesh K.

Accepted Solutions (0)

Answers (1)

Answers (1)

madhusap
Active Contributor
0 Kudos

Hi Rupesh,

When you created your root org.hierarchy you will give Valid From and To date to it. Please check if your Mitigation control ID valid date and that date has any conflicts.

Check root org.hierarchy details from NWBC -> Master Data -> Organizations.

Regards,

Madhu.

Former Member
0 Kudos

Hello Madhu,

Could you help us with a issue like Rupesh have?

We want create a control and when we pass the first to the second tab, the error ‘Valid-to’ date cannot be later than that of the parent Object appears.

We check organizations and we have the following dates:

From:05.10.2015

To:31.12.9999

and for the risk that we want mitigate, have the following:

From:03.11.2015

to:02.11.2016

We changed the date of the risk several times, but the error persist.

What we can do?

Thank you.

Regards,