on 02-07-2014 12:07 PM
Hello Experts
I can't transfer request order with services master record from ECC to SRM.
I can transfer request order with 4 different account assignment category :
Request order with account assignment category N ( Network ) ----> OK
Request order with account assignment category F ( Financial center ) ----> OK
Request order with account assignment category A ( fixed asset ) -----> OK
Request order with account assignment category P ( Project) ----> OK
Request order with account assignment category P ( Project ) and item (P) Services record ----> NOT OK
I don't anderstand why i can't transfer the request order with services master record.
When i check on NWBC SRM, i have all my services record.
When i transfer with SE38 and the program BBP_EXTREQ_TRANSFER. I go to SMQ1 and the system give me this error message
Please i need your help.
Best regard
Hello ,
Have you changed the date of PR before transferring or was the delivery date greater than transfer date of BBP_EXEREQ_TRANSFER.Please do confirm and let me know . Also would suggest to check you queues are they stuck there.
If you find any in queue delete it and again create a fresh new PR note( do maintain the date properly) and while transferring through the report please maintain the transfer date 31.12.9999 and then check it.Also can you tell me what was the status of PR before transferring into table EPRTRANS.
Thanks
Gaurav Gautam
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Hi,
why don't you check application log (SLG1) fro that
Regards
Konstantin Anikeev