on 02-06-2014 8:17 PM
Hello ,
Can we do rough cut capacity planning in PPDS and how can we achieve it .
Regards,
Nick
Hi Nick,
Rough cut capacity planning can be done in SNP. SNP planning is rough cut planning which plan in the buckets. It is not possible in PPDS. PPDS planned order it will be a detailed level of planning which will explode all operations and your order.
Regards,
R.Brahmankar